30th Street: The right lane of 30th Street heading northbound will have intermittent lane closures between Walnut and Mapleton streets through July 2022 during construction of the Pollard Jeep site development. Arrow boards and signage will be used to direct traffic.

North Broadway: North Broadway will continue to accommodate two-way traffic between Violet Avenue and U.S. 36 during a potholing, boring and utility relocation project, but parking restrictions will be in place, and cyclists will have to merge with traffic through the construction area.

Nineteenth Street: 19th will be closed south of Arapahoe through April 7 for a ditch maintenance project. A detour will be in place.

Longmont

County Line Road: The widening and installation of left-turn lanes and intersection improvements and other work on County Line Road between Ninth and 17th avenues is underway and scheduled to be completed in April.

Main Street (U.S. 287): The Colorado Department of Transportation is working on adding a northbound U.S. 287 lane between Pike Road and a point about 1,000 feet south of Pike Road and Main Street.

Boulder County

71st Street: 71st Street is closed in both directions between Glacier View Road and Winchester Circle. Access to businesses in the Gunbarrel Tech Center off Winchester Circle will be maintained from 71st Street via Colo. 52 on the north. The project is expected to last through the end of March.

U.S. 287 and Isabelle Road: Travelers on both U.S. 287 and Isabelle Road can expect lane closures and traffic shifts until May as part of an ongoing intersection improvement project. Work will be from 8 a.m. to 4:30 p.m. Mondays through Fridays. Weekend work may be necessary over the course of the project, which is expected to last until May.

61st Street: A culvert replacement project is reducing 61st Street lanes between Jay and Valmont roads, with delays expected through May.

Baseline Road: A culvert replacement project is currently in progress on Baseline Road just east of Cherryvale Road. In addition, Xcel Energy will be working in the same area to replace some of their underground infrastructure. Work will take place between 8 a.m. and 4:30 p.m., Monday through Friday. Travelers along the road can expect lane closures and travel delays during working hours. A temporary traffic signal will be used at night and on weekends as the road will be reduced to one lane 24 hours a day, seven days a week. A full road closure may be necessary to perform certain aspects of the work. More information will be posted should the road need to be closed. The project is anticipated to last into later this spring or into the summer.

Erie

U.S. 287, Arapahoe Road: Improvements on the west side of the intersection at U.S. 287 and Arapahoe Road in the Colorado Department of Transportation highway right of way is underway as part of the Nine Mile Commercial Subdivision project. The initial construction will be demolition and grading activities followed by construction of the island and a turn signal and associated utilities. This portion of the work is expected to last until Aug. 5. The construction will involve lane closures of the eastbound turn lane on Arapahoe Road onto southbound 287.