Colonial says gasoline line safely restarted after leak

Vehicles wait in line for gas at a Twice Daily gas station on Franklin Road in Brentwood, Tennessee, U.S. September 17, 2016. REUTERS/David Mudd

NEW YORK (Reuters) - Colonial Pipeline Co [COLPI.UL] said its main gasoline line, Line 1, was safely restarted and returned to service on Wednesday after its biggest leak in nearly two decades squeezed supply and led to increased prices at the pump in the Southeast United States.

The biggest refined products system in the United States restarted parts of the line a few days after a leak was discovered on Sept. 9. The damaged section of the 1.3 million-barrel-a-day line that connects the refining hub of the Gulf Coast to the East Coast has been shut for more than 12 days.

"Subsequent to this afternoon's successful restart, it is expected to take several days for the fuel delivery supply chain to return to normal," Colonial said, adding some markets served by it may experience intermittent service interruptions.

Motorists have faced long lines and shortages of fuel in many states across the Southeast, such as North Carolina and Tennessee.

Consumers are expected to feel the pinch for slightly longer, until the supply chain is fully restored after the 6,000-8,000 barrel leak in Shelby County, Alabama.

Prices in Georgia, one of the most affected, inched up by another cent on Wednesday, with a gallon of regular gasoline currently at $2.372, about 28 cents higher than last week's average prices, according to motorist advocacy group AAA.

The outage led to a record drop in inventories in the East Coast and sent Gulf Coast gasoline stockpiles soaring to record highs.

The company built a section of pipe to bypass the damaged portion, in order to restart operations quickly. The U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration, or PHMSA, approved the operation of the bypass as a temporary measure to restore service, late on Tuesday.

That approval does not affect the terms of the Corrective Action Order PHMSA issued on Sept. 16.

Colonial said it successfully tested and completed the connection of the bypass segment to the main line on Wednesday morning.

After the line is restarted, Colonial will work with federal, state and local officials to remove the damaged segment of the original line and try to determine the cause of the leak. It was discovered on Sept. 9 by a mining inspector who smelled a fuel odor.

(Reporting by Devika Krishna Kumar in New York and Vijaykumar Vedala in Bengaluru; Editing by Chris Reese and Peter Cooney)