Louisiana lags on electric vehicle charging program, but DOTD sees ‘no reason to rush’

Electric car plugged into charging station
Electric car plugged into charging station

A Jaguar electric vehicle charges its battery at a rural EV charging station in Abita Springs, La., on June 1, 2024. (Photo credit: Wes Muller/Louisiana Illuminator)

Two years after receiving federal funding to build electric vehicle charging stations across the state, Louisiana has yet to ask for bids from companies that might want the money. However, state transportation officials say there is a reason for their sluggish pace. 

The Louisiana Department of Transportation and Development (DOTD), plans to start the request-for-proposal process as soon as it identifies an appropriate “contracting mechanism” under state law to use the money, DOTD spokesperson Rodney Mallett said. 

The Federal Highway Administration allocated $73.4 million to Louisiana under the National Electric Vehicle Infrastructure (NEVI) program in 2022. NEVI is a product of the Bipartisan Infrastructure Law that Congress approved in 2021. It included billions for state transportation agencies to build a network of rapid chargers along major highways. 

Louisiana’s initial response was on par with other states. DOTD submitted its NEVI deployment plan by the federal deadline of August 2022. However, while states such as Ohio, Pennsylvania and others now are disbursing the grant money or have already built some EV charging stations, Louisiana hasn’t yet figured out how to spend it. 

“There’s no real reason to spend two-plus years figuring out how to get this money to grant recipients when other states are already opening up chargers,” said Ryan McKinnon of the Charge Ahead Partnership, an EV charger lobby group. “Lots of states will be opening up chargers pretty soon, and it sounds like Louisiana will be sitting on the sidelines.” 

McKinnon said Louisiana is one of 15 states that have still not asked for bids to use the NEVI grant money. 

Some congressional Republicans and anti-union groups have directed their criticism at the Biden administration, claiming the delays are the result of mismanagement or of labor requirements within federal rules. Officials closest to the situation say the delays are largely because it is a new program that they want done correctly.

Mallet said the federal rules for the NEVI program don’t “fit cleanly” within DOTD’s usual contracting methods. DOTD often writes contracts for projects in which the agency owns and maintains the infrastructure, such as highways. In contrast, the EV charger grants will pay for the construction of infrastructure for which “ownership and operation will be transferred” from the state, in most cases, to a private entity, he said.

Although the Biden administration has aimed for a goal of building 500,000 charging stations by 2026, Mallet said the NEVI funds do not lapse, so there is no hard deadline to complete the projects.

“The key is to do it right for the long term,” Mallet said. “No reason to rush it through.”

Tyler Herrmann with Louisiana Clean Fuels, a nonprofit working with DOTD on the NEVI rollout, said smaller EV charger programs of the past saw build-outs at sites that weren’t very practical. 

The chargers were often installed at public libraries or apartment complexes — places with no real interest or resources to maintain them. Without that routine maintenance, chargers would break and often stay that way for years. 

The government learned from those programs and is now taking care to avoid making those same kinds of mistakes, Herrmann said.   

“It is a unique situation,” Herrmann said of DOTD’s efforts to administer the NEVI grants. “The program is pretty much completely different from what the DOTD does normally.”

In the meantime, Louisiana Clean Fuels has been working to build a workforce of technicians who can install and repair EV chargers and supply equipment.

Baton Rouge Community College just recently saw its first class of students graduate from a three-week course in which they learned some of the fundamentals required to become nationally certified Electric Vehicle Supply Equipment technicians. 

Herrmann said about a dozen students completed the first course, which will soon be offered at other community colleges across the state.

Correction: Ryan McKinnon said Louisiana is one of 15 states that have still not asked for bids to use the NEVI grant money. A previous version of this article cited an incorrect number of states. 

The post Louisiana lags on electric vehicle charging program, but DOTD sees ‘no reason to rush’ appeared first on Louisiana Illuminator.