Yearslong effort to widen Wales Road NE in Massillon enters home stretch

Motorists travel on Wales Road NE at Hankins Road NE last week in Massillon. About 95% of the Wales Road repaving and widening project is completed.
Motorists travel on Wales Road NE at Hankins Road NE last week in Massillon. About 95% of the Wales Road repaving and widening project is completed.

MASSILLON – A multiyear effort to widen and improve Wales Road NE is heading down the home stretch.

Altogether, the work has been part of a $7.2 million project to resurface and widen a 1.4-mile section from Lincoln Way E to Hills and Dales Road NE. The scheduled completion date is July 31.

"I'd say we're about 95% of the way home," said Justin Chesnic, an Ohio Department of Transportation public information officer for District 4, which includes Massillon. "Most of what's left to do is off the road."

Motorists travel north and southbound Thursday on a newly resurfaced and widened Wales Road NE in Massillon. The project to redo a 1.4-mile stretch of the road started in early 2021.
Motorists travel north and southbound Thursday on a newly resurfaced and widened Wales Road NE in Massillon. The project to redo a 1.4-mile stretch of the road started in early 2021.

Some primary tasks remaining include a final striping of the roadway, smoothing over some asphalt and updating traffic signals at intersections, Chesnic said.

The project also includes new sidewalks, landscaping, curb and gutter replacement, and new traffic lights.

Road redo: Massillon's $2.54M street repaving plan to fix parts of 49 streets in 2024

The majority of work has been grant funded, as the city is picking up around $1.4 million. The city's share came out of the Massillon Marketplace tax increment financing district.

Construction was put on hold last December by ODOT as a winter safety precaution.

The work kicked off in January 2021 with tree removal and utility work. ODOT came on-site a year later.

The effort hit a standstill in parts of 2022 because of supply chain issues for equipment and materials from the COVID-19 pandemic.

Most of the Wales Road NE repaving and widening project in Massillon has been completed.
Most of the Wales Road NE repaving and widening project in Massillon has been completed.

But city Engineer Alex Pitts said the project has been back on track for some time, calling it 90% to 95% finished.

He noted some "punch-list" items are remaining, which likely would be addressed in a final inspection in late July. That may include adjusting manhole covers and adjusting traffic light sequences.

"The majority of things are done. We like how work has been progressing," Pitts said.

Reach Steven at steven.grazier@indeonline.com. On X: @sgrazierINDE

This article originally appeared on The Independent: Project to upgrade, widen Wales Road NE in Massillon nears finish line