Roundabout No. 16 to be built at Cosgray Road and Woodsview Way

The Hilliard Municipal Building is at 3800 Municipal Way.
The Hilliard Municipal Building is at 3800 Municipal Way.

Construction is to begin early next year on a traffic roundabout at Cosgray Road and Woodsview Way, near the Hoffman Farms subdivision and the Hilliard/Ray Patch Family YMCA.

It is to be Hilliard’s 16th roundabout.

The intersection currently has a stop sign for traffic on Woodsview Way.

Hilliard City Council on Oct. 24 adopted a resolution authorizing construction of the roundabout.

Miller Brothers Construction Inc. submitted the lowest and best bid of $3.59 million and was awarded the contract, according to Hilliard Assistant City Manager Dan Ralley.

The company’s bed was “significantly below” the city engineer’s estimate of $4.4 million, Ralley said.

Hilliard received a $1 million grant from the Ohio Public Works Commission that will cover almost 25% of the project’s total cost, Ralley said.

Six companies submitted bids that the city opened Oct. 6, ranging from the low bid of $3.59 million to $4.3 million.

The city has not previously contracted with Miller Brothers Construction Inc. and references were thoroughly investigated, Ralley said.

The contract includes a 10% contingency and sets a maximum not-to-exceed amount of $3.95 million.

Professional services by another company, Prime AE Group, that includes contract administration, construction project management, inspections and material testing, in the amount of $354,000, raises the project’s cost to $4.3 million.

Cosgray Road will be fully closed next summer, while schools are not in session, to complete the project, Ralley said.

The project is expected to be “substantially complete” by mid-August 2023, according to Ralley.