St. Johns County to celebrate $6.76 million Hastings wastewater treatment plant improvement project
St. Johns County will hold a ribbon-cutting ceremony to celebrate the completion of the $6.76 million improvement project for the Hastings wastewater treatment plant located at 900 N. Main St.
>>> STREAM ACTION NEWS JAX LIVE <<<
The improvements included replacement and upgrade for the plant to handle additional capacity to handle peak flows due to storm events. It also addresses raised critical equipment above the flood elevation and improved reliability and redundancy for maintenance and emergency response activities.
[DOWNLOAD: Free Action News Jax app for alerts as news breaks]
Other improvements include:
Site work/civil improvements to improve vehicular travel
Surge tank improvements
New biological nutrient removal (B.N.R.) tank with two trains utilizing the 4-Stage Bardenpho process with internal recycle pumps, blowers, mixers, diffusers, and post-aeration aerator
Routing of the existing micro-C glycerin and proposed alum feeds from the chemical storage building to the B.N.R. tanks for carbon addition and phosphorus removal
Upgraded mechanisms in the secondary clarifiers
New RAS/WAS pump station, piping, valves, and appurtenances
New tertiary filtration system
All new electrical wiring plus a standby generator for the site
New controls for existing and proposed equipment
The budget for this product totaled $6,760,000.