Third nuclear reactor reaches 100% output at Georgia’s Plant Vogtle, which will provide power to JEA

A new reactor at a nuclear power plant in Georgia has reached its full power output for the first time and is scheduled to enter commercial operation within the next month.

Georgia Power Co. announced Monday that Unit 3 at Plant Vogtle, southeast of Augusta, has reached its full output of 1,100 megawatts of electricity. That’s enough to power an estimated 500,000 homes and businesses. The power will be sent to Georgia and other states.

>>> STREAM ACTION NEWS JAX LIVE <<<

Operators are conducting further testing to prove they can run the reactor in ways required for regular operations, Georgia Power CEO Kim Greene in a statement, calling the achievement “an exciting milestone.”

“It tells us we’re close to finishing the unit safely and bringing it online to power Georgia homes and businesses with reliable, emissions-free energy for decades to come,” she said.

READ: Debt ceiling plan will end student loan payment pause; what does that mean for borrowers?

The fourth reactor has finished a key testing phase and operators expect to start loading radioactive fuel between July and October, aiming for the reactor to reach commercial operation between December and March 2024.

Units 3 and 4 at Plant Vogtle are the first new reactors built from scratch in decades in the United States.

The first two reactors have been generating electricity at Vogtle for decades. A third and a fourth reactor were approved for construction at Vogtle by the Georgia Public Service Commission in 2009, and the third reactor was supposed to start generating power in 2016.

[DOWNLOAD: Free Action News Jax app for alerts as news breaks]

The cost of the third and fourth reactors was originally supposed to be $14 billion, but are now on track to cost the owners $31 billion. That doesn’t include $3.7 billion that original contractor Westinghouse paid to the owners after going bankrupt, which brings total spending to almost $35 billion.

In Georgia, almost every electric customer will pay for Vogtle. Georgia Power, the largest unit of Atlanta-based Southern Co., currently owns 45.7% of the reactors. Smaller shares are owned by Oglethorpe Power Corp., which provides electricity to member-owned cooperatives, the Municipal Electric Authority of Georgia and the city of Dalton. Oglethorpe and MEAG plan to sell power to cooperatives and municipal utilities across Georgia, as well as JEA in Jacksonville, Florida, and parts of Alabama and the Florida Panhandle.

JEA says on its website that the “expansion of Georgia’s Plant Vogtle nuclear power facility, with Units 3 and 4, will provide carbon-free electric power to consumers in Georgia and JEA customers in Northeast Florida.”

[SIGN UP: Action News Jax Daily Headlines Newsletter]

“In the long term, this will be a positive carbon-free investment for our Northeast Florida customers and the environment,” Jay Stowe, JEA Managing Director and CEO, said in a statement on the utility’s website.

Georgia Power’s 2.7 million customers are already paying part of the financing cost and elected public service commissioners have approved a monthly rate increase of $3.78 a month for residential customers as soon as the third unit begins generating power. That could hit bills in July, a month after residential customers see a $16-a-month increase to pay for higher fuel costs. Georgia Power also raised rates by 2.5% in January after commissioners approved a separate three-year rate plan. Increases of 4.5% will follow in 2024 and 2025 under that plan.

Commissioners will decide later who pays for the remainder of the costs of Vogtle, including the fourth reactor.